This week was a short 3 day work week, but the nice sunny weather is back. The second story really started taking shape this week. On Monday and Tuesday, the guys set up the moulds and all of the steel rods and window outlines. The process is the same as with the previous two floors. On Wednesday they poured the concrete, which was able to dry nicely over the 4 day weekend.
The other big thing that happened was the scaffolding went up. You may be asking yourself isn't it alittle late, the answer…yes, yes it is. I have mentioned it a couple of times that HUG is ahead of schedule. Because of this Albert ordered the scaffolding to arrive too late. So HUG has found ways around it, but at least for the rest of the workers there will be a safer option to install items around the house. The Scaffolding will be completed on Monday.
Thanks again for stopping by!!