Schönenberg An Der Thur, Switzerland
Rightfully so I have been getting many people asking about the status of our house. I am sorry that I haven't posted anything in almost two months!! The month of August was a slow month for the house building. We left off just before the "building holidays" (which are typically three weeks). To trigger some memories, right before the holidays they sprayed in the sub floor. This needed a week per cm of floor to dry, meaning for our 8 cm we needed 8 weeks. Therefor...